![]() ![]() |
|
![]() |
Liner rehabs gas main At 7,000 ft, KeySpan’s renewal of a 20-in. cast iron pipe is the largest cured-in-place lining job in the United States Allen Spivey, Gas Technology Institute, Des Plaines, Illinois When KeySpan Corp. was notified that New York’s DEP Water Department was planning a large-scale construction project to replace a 16-in. pipe that was in close proximity to its 20-in. cast iron gas main, they immediately started to look at their options. In addition to the water pipe replacement work, KeySpan was notified that traffic would be diverted around some of the large excavations, but over the existing gas main. Other than a small number of joint leaks, the 20-in. bell and spigot pipe had provided good service for many years, and had been expected to provide many more. However, with considerable trenching near the gas main as well as vibrations and increased loads from traffic, KeySpan operations staff knew that the risks of more leaks along the gas pipe would be much greater. Furthermore, a substantial amount of street restoration would follow the water pipe replacement project. KeySpan also knew that something had to be done with the gas main before the street work was started. Several repair and replacement methods were considered. There would be the potential for both horizontal movement due to parallel trenches, vertical movement due to weakened beam support from perpendicular trenches under the cast iron pipe, and new traffic loads associated with the water main construction. Joint sealing methods that had not been proven reliable for the substantial movement anticipated were eliminated as maintenance alternatives. The choices would be to either replace the pipe or to use cured-in-place lining to ensure joint integrity even after the water pipe construction. Replacement was ruled out because of the lack of adequate right-of-way space to add a new line (unless the existing pipe was extracted). It was also ruled out due to the increased risk of damaging other buried facilities while trenching in the new large-diameter pipe, because of the estimated relative high cost of a new pipe. Cured-in-place lining offered a number of benefits. Fewer excavations would be needed, so restoration liabilities and costs would be reduced, disruption to traffic and businesses would be limited, the risk of damaging other buried utilities would be all but eliminated, and the cost of renewal would be considerably less than replacement. KeySpan was one of the early pioneers in lining, and felt confident that Progressive Pipeline Management, the contractor, using the Starline® liner product, would meet their needs. At roughly 7,000 ft, the KeySpan 20-in. cast iron pipe lining project represents the longest gas lining job in the United States to date. The gas main was located in Brooklyn, New York, mostly along a busy thoroughfare, Flushing Avenue. About 5,000 ft of the main operated at 15 psig, and the other 2,000 ft at low pressure (inches water column). Once lined, all of this primary gas supply artery would be operated at 15 psig. Sections of the pipe were replaced if they were extremely close to the water pipe, or would be too shallow once other construction and grading work was completed. The lining project was complicated, because KeySpan restricted the length of some inversions (typically 500 to 700 ft) to as short as 250 ft to limit customer outages, and due to work-time restrictions that required the lining to be completed early in the day. The flexibility of the product was demonstrated when successfully lining sections of pipe that had four to six offsets. Even ancillary tools, cleaning equipment and robots performed outstandingly in preparing the pipe and in reinstating services. Lining started in October 2003, paused due to weather, then, resumed in March before finishing in April 2004. KeySpan was pleased with results of the lining job, and expects to operate this large-diameter main for many years to come. “We expect to have more of these types of projects and based on the success we’ve with starline®, lining the pipe will be considered a viable if not a preferred maintenance option,” says Susan Fleck, KeySpan. Background Benefits The starline process benefits gas utilities by: The lining process Lining applications Natural gas mains (up to 60 psi) are rehabilitated with the starline® 200 technology. In the case of pipes from 4 to 24-in. diameter, pipe segments that are not easily accessible to construction vehicles can be renewed using mobile lining equipment. The actual lining procedure can be completed in approximately one hour for sections up to 700 ft, with the total process taking from 12 to 24 hours. The pressure drum can be disconnected from the line so that additional sections can be rehabilitated with a single set of installation equipment in one working day. The specially developed cleaning technique and proprietary resin adhesive allow the fabric hose to be uniformly bonded to the interior wall of the pipe, ensuring the high quality of the rehabilitation. Status
|
|
| ©2005-2008 Kerr Engineered Sales Co. | Site Designed and Developed by ckarma inc. |